Tag Archives: managing benefits

what good can projects do if you can’t tell if the expected benefits are met when they complete ?

2 Juil

« Less than 20% of organizations can say that they have high benefits realization maturity »

Arras 2016 BenchmarkHe is a disturbing observation you’ll discover in the Arras Project Management Benchmark Report 2016

Back for the 11th year, the Project Management Benchmark Report from Arras People is an independent survey into the lives and careers of PPM practitioners.

While projects are undertakn to achieve certain expected benefits 4 ou of 5 companies are not matured enough in their benefits realization process to tell with certainity which project brought or not these adavntages to the business.

Other aspects covered in the report relate to the adoption of Agile, the importance of recognized PPM accreditation, professional affiliations, career development, PMOs, role of women in PMOs…

The report is now available to download

Partenaire de DantotsuPM

Partenaire de DantotsuPM

le chef de projet devrait toujours prêter attention à la réalisation des bénéfices

4 Mai

A Project Manager Should Always Keep an Eye on Benefits Realization

http://www.projecttimes.com/kiron-bondale/a-project-manager-should-always-keep-an-eye-on-benefits-realization.html par  Kiron Bondale

La triple Contrainte

la triple Contrainte

La gestion de la triple contrainte est seulement le service de base, il est grand temps pour les chefs de projet d’aller plus loin.

La préoccupation naturelle qui pourrait être soulevée est que, dans de nombreux cas, le chef de projet est passé au projet suivant alors que le propriétaire de produit (Product Owner) et certaines autres parties prenantes travaillent encore à assurer que le changement requis pour réaliser des bénéfices est bien effectif. Le chef de projet pourrait avoir eu un engagement direct limité avec le personnel qui doit adopter les changements, ou pourrait n’avoir aucune influence sur les facteurs externes qui auraient un impact sur la réalisation desdits bénéfices.

Ceci est tout à fait vrai, et pourtant, si le projet ne délivre pas les bénéfices attendus, le chef de projet va probablement recevoir une partie du blâme.

Responsabilités

assumer ses responsabilitésCeci ne veut pas dire que les chefs de projet n’essayent pas de poser les bases du réel succès après avoir complété leurs projets. Parfois, la faute pourrait revenir aux propriétaires de produit susceptibles de percevoir de tels efforts du chef de projet comme une intrusion dans leur juridiction. Cependant, ceci n’est en aucune manière une raison suffisante de reculer pour le chef de projet. Si il a une preuve suffisante que la réalisation des bénéfices sera impactée, c’est sa responsabilité de s’assurer que ces informations sont prises en compte.

Initiation du projet

Pendant l’initiation du projet, le chef de projet devrait prendre le temps de comprendre le cas d’affaires qui soutient le raisonnement du sponsor d’investir dans le projet. Ceci est un des avantages à avoir un chef de projet qui ait un peu d’expertise du domaine. Un chef de projet qui a seulement une compréhension superficielle des processus métier va probablement moins comprendre si certaines suppositions fondamentales sont invalides. Il pourrait éluder des menaces qui auraient un impact sur la réalisation réussie des bénéfices.

Un analyste d’affaire est d’habitude responsable de l’élicitation de besoins et devrait vérifier que les besoins collectés sont directement connectés au cas d’affaire et aux retours attendus. Et, le chef de projet devrait aussi prendre le temps de passer en revue la ligne de bases des besoins comme cela dicte beaucoup de décisions en aval qui peuvent avoir un impact sur le succès de projet. En faisant ceci, le chef de projet est mieux équipé pour supporter l’analyste d’affaire dans la facilitation de la prise de décisions appropriées – quand les changements de portée interviennent plus tard dans la vie du projet.

Pour les projets dont on attend livrer des avantages financiers, le chef de projet devrait non seulement se concentrer sur la définition des coûts du projet, mais devrait aussi passer en revue les coûts opérationnels récurrents et les projections de revenu estimées par le propriétaire de produit et autres parties prenantes. Si les suppositions à la base de ces évaluations ne semblent pas être correctes ou si le chef de projet croit qu’une contrainte clé pourrait avoir été manquée, il devrait partager cette préoccupation.

Réalisation / Construction

straight line train railtrackUne fois que le travail a commencé pour livrer le contenu approuvé du projet, la plupart des chefs de projet ont tendance à concentrer leurs efforts sur garder le projet sur les rails et manager efficacement des demandes de changements par rapport aux lignes des bases. Pour complémenter ces activités normales de projet, le manager de projet devrait envisager de prendre le temps de revisiter périodiquement le cas d’affaires pour identifier les changements qui peuvent avoir un impact sur l’atteinte des bénéfices attendus.

Le chef de projet peut aider à faciliter des revues des bénéfices avec le propriétaire de produit en identifiant et en engageant les bonnes parties prenantes qui peuvent fournir un apport dans le processus d’évaluation. Si le chef de projet et le propriétaire de produit décident qu’il y a eu une réduction significative des bénéfices escomptés, ceci devrait déclencher une revue avec le l’entité de gouvernance appropriée pour se décider si le projet devrait continuer à être financé pour éviter d’y investir davantage à fonds perdus.

Campana & Schott est partenaire de DantotsuPM

Campana & Schott est partenaire de DantotsuPM

Maîtrise des changements

jeter l'argentLes changements de périmètre fournissent une autre occasion pour les chefs de projet d’aller au-delà de leur rôle traditionnel de livraison de projet. Alors que comprendre les impacts sur le contenu, l’échéancier, les coûts et les contraintes secondaires de projet est important, les impacts sur la réalisation des bénéfices devraient aussi être identifiés pour éviter des conséquences inattendues.

L’adoption réussie de changement et leur suivi sont un autre apport critique dans la réalisation des bénéfices. Les meilleurs livrables de projet produiront une valeur minimale si le personnel opérationnel ne modifie pas ses comportements pour tirer le plein avantage des changements.

Communications

A travers ses interactions régulières avec les parties prenantes, le chef de projet est dans une position idéale pour recevoir un retour d’information des groupes impactés par les changements.

Le chef de projet peut supporter des propriétaires de changement dans l’analyse des parties prenantes et des plans d’action et peut assurer que la priorité est placée pour garantir que les agents de changement nécessaires sont inclus pour chaque domaine. Il peut passer en revue des plans de changement et aider à faciliter l’identification de risques et l’animation ses sessions d’évaluation requises pour comprendre quelles menaces peuvent exister qui entraveraient une adoption réussie.

MPM est Partenaire de DantotsuPM

MPM est Partenaire de DantotsuPM

Je n’oublie pas l’effort et les défis à surmonter pour réussir un projet sur un contenu, un coût et des délais approuvés, mais ce n’est pas suffisant de nos jours.

Qu’on le veuille ou non, vous serez probablement évalués non seulement sur la livraison de projet, mais aussi sur si vos projets ont délivré les bénéfices attendus.

Un projet est-il complet sans la réalisation des bénéfices ?

22 Déc

Is a Project Complete Without Benefits Realization?

http://www.pmhut.com/is-a-project-complete-without-benefits-realizationzation Par Terry Melnik

Dans notre conduite de projet quotidienne et activités PMO, la chose la plus facile à manquer et la plus importante est de prévoir AVANT ce qui arrive APRÈS que nous franchissions la ligne d’arrivée. Techniquement, une fois que le chef de projet remet les rênes du projet achevé au chef d’entreprise, son travail est seulement à moitié fait. Pour qu’un projet soit considéré complet, les chefs de projet doivent se concentrer sur l’autre moitié : « la Réalisation des bénéfices ».

La réalisation des bénéfices est la confirmation que la valeur attendue du projet a vraiment été délivrée.

APMG Managing BenefitsDans notre management de projet quotidien, il est facile d’être noyé dans les détails autour de la gestion des tâches, la réduction des risques, la gestion de la capacité en ressources, l’équilibrage des budgets et tous les autres éléments en mouvement. Nous oublions souvent pourquoi, en premier lieu, nous avons l’intention de faire le projet : livrer un produit ou un service, une amélioration ou une nouvelle capacité.

Par exemple, respecter un nouveau règlement, répondre à une demande standard ou au marché.

Mais si, après avoir construit et livré les produits qui font exactement ce que le client a demandé, nous nous rendons compte que tout l’effort et les ressources que nous avons consommés sur le projet ne produisent pas à ce à quoi l’on s’attendait ?

C’est exactement ce qu’est la réalisation des bénéfices.

squeezed money

Des investissements sous surveillance

Nous avons tous entendu parler de ROI (« Return On Investment » – retour sur l’investissement). C’est le concept selon lequel un investissement d’une certaine combinaison de ressources (des gens, de l’argent, de l’équipement, etc.) apporte un avantage, un bénéfice à l’investisseur. Un fort ROI signifie que les gains balancent très favorablement l’investissement. Comme mesure de performance, c’est l’une des meilleures méthodes pour évaluer l’efficacité d’un investissement. Le ROI ne doit pas exclusivement être exprimé en termes financiers. Ce peut être un avantage opérationnel, une amélioration de la position commerciale, ou autre changement positif. Pour comparer l’efficacité d’un certain nombre d’investissements différents, nous devons comparer des métriques, c’est pourquoi le ROI financier est l’un des plus couramment utilisés. Malheureusement, sans réalisation des bénéfices, notre ROI est seulement une conjecture. Et c’est pourquoi la réalisation des bénéfices est si importante.

J’en ai discuté avec beaucoup de nos clients et j’ai découvert qu’il y a une grande variété de niveaux de maturité autour du processus de réalisation des bénéfices. Ceci est une indication que, tandis que le concept de réalisation gagne en intérêt, c’est toujours loin d’être une pratique mature. Voici qui présente une excellent opportunité pour les organisations qui ne le font pas encore et maintenant est le bon moment pour implémenter cette pratique.

Partenaire de DantotsuPM

Partenaire de DantotsuPM

Comment lancer une initiative de réalisation des bénéfices ?

L’une des meilleures approches est de se définir des objectifs, de mettre en place un suivi de ces objectifs et incluant une étape de « laisser faire », semblable au passage du bâton dans une course de relais Olympique.

"Image courtesy of Stuart Miles / FreeDigitalPhotos.net"

« Image courtesy of Stuart Miles / FreeDigitalPhotos.net »

Vos étapes tactiques peuvent inclure:

Définissez votre cible

En utilisant une méthode de calcul disponible, combinée avec l’expérience et validée par des résultats de projets similaires, décidez d’un objectif de la valeur que vous pensez que le projet livrera. Posez-le comme estimation initiale. Engagez l’aide d’un directeur ou d’un contrôleur financier pour aider à bien positionner ces évaluations originales.

Contrôlez continuellement

surveillanceEn utilisant les évaluations ou objectifs initiaux comme première conjecture, continuez à affiner les facteurs de succès pendant tout le cycle de vie du projet. Ceux-ci sont souvent appelés re-prévisions (« reforecast ») et engagés (« committed ») et sont plus précis que les estimations originales. Il est préférable de continuer à réviser ces chiffres pendant tout le projet. Ici, l’objectif est d’avoir des chiffres prévisionnels qui correspondent quasiment aux données réelles.

Commencez maintenant à suivre les données réelles

Un projet peut en réalité produire des bénéfices avant même d’être fini. Quelle belle victoire pour l’équipe projet que de pouvoir se prévaloir de ceux-ci.

Mettez un plan en place

chrono5 afterAjoutez un jalon ou une étape au-delà de l’étape ‘fin’ appelée ‘clôture’ ou ‘réalisation’ et mettez une étape de validation 3, 6 ou 12 mois après que le projet soit complété. Cela pose l’attente que le travail n’est totalement terminé à l’étape ‘fin’.

C’est en dehors de la responsabilité du chef de projet

volunteerComme le projet approche sa date ‘Complet’ ou ‘Fin’, engagez le sponsor financier et le propriétaire de processus (la personne qui bénéficie ou possède le résultat du projet ou le livrable, que ce soit une amélioration ou un changement) et faites-leur commencer à valider et « posséder » les chiffres.

Revenez au point de départ

retour sur investissementQuelle était la précision de vos évaluations originales comparée aux données réelles ? Prenez ces enseignements et appliquez-les aux futures estimations. Ceci est appelé l’amélioration continue – l’application de leçons apprises et des bonnes pratiques pour améliorer tout le PMO.

Un dernier point est que le bénéfice n’est pas toujours de l’argent.

Parfois les projets produisent une autre valeur, comme une amélioration de la satisfaction client, ou une augmentation de parts de marché en lançant un produit qui change la donne. Il est important de pouvoir quantifier la valeur de ces types de projets même s’ils ne produisent pas de revenu direct ou réductions de coûts. Beaucoup d’organisations appellent ceux-ci des bénéfices de ‘Niveau 2’ou ‘Indirects’.

Finalement, un projet est-il complet sans réalisation des bénéfices ?

Image courtesy of stockimages at FreeDigitalPhotos.net

Image courtesy of stockimages at FreeDigitalPhotos.net

Du chef de projet qui a déjà terminé son marathon et marqué le projet comme complet, je m’attends à ce que sa réponse soit « OUI », mais le bon sens en dit autrement. Comme bonne pratique, un des facteurs les plus importants dans la réussite du projet n’est pas « comment nous l’avons fait » – dans les temps et conformément au budget – mais « ce que nous avons fait » – que le projet a délivré ce qu’il avait eu l’intention de faire.

February 24 – Webinar (PMI) – What’s the most important aspect of Project Management?

13 Fév

A PMI New Practitioners Community of Practice Webinar with Mark Phillipy

Delivering Business Value: The Most Important Aspect of Project Management

La figure 1 : la triple Contrainte

la triple Contrainte

24 February12-1 PM EST (18:00 CET/France)

In the past, success of a project was measured based on its ability to deliver a quality scope on time and within budget. Although these factors are important to consider and control as a project progresses they are not a true measurement of the success of a project. A project can only be considered successful if that project delivers the predetermined business value to the customer. When we look at project success in this light, businesses will make better decisions about which projects to execute and project managers will focus on what is important as their team delivers value.

Partenaire de DantotsuPM

Partenaire de DantotsuPM

Delivering business value to the customer is the most important aspect of project management. Through the use of story and real life examples this practical session will help solidify your resolve to be a successful project manager by focusing on delivering value to your customers and business. You will also learn the five steps to delivering business value and how to apply those steps to your future projects.

Partenaire de DantotsuPM

Partenaire de DantotsuPM

 

Revue du livre “A senior manager’s guide to managing benefits” de Stephen Jenner

3 Fév

“A senior manager’s guide to managing benefits” by Stephen Jenner

http://hennyportman.wordpress.com/2013/01/25/book-review-a-senior-managers-guide-to-managing-benefits-by-stephen-jenner/  par Henny Portman

APMG Managing BenefitsLe management des bénéfices est toujours un point faible dans beaucoup d’organisations. Les méthodes comme PRINCE2 avec le Plan de Revue des Bénéfices ou MSP avec les thèmes Management des bénéfices ou Réalisation des Bénéfices aident sur ce point, mais il semble que ce ne soit pas suffisant. Il y a maintenant une nouvelle norme « Managing Benefits » incluant un examen de fondation et un de Praticien par APMG.

Pour comprendre ce standard, il existe deux livres. Le guide de praticien Managing Benefits et le guide de management exécutif A senior manager’s guide to managing benefits (optimizing the return from investments). Stephen Jenner a écrit les deux livres.

Senior managers guide to managing benefitsA senior manager’s guide to managing benefits est un petit livret (51 pages) pour les cadres exécutifs et il adresse la gestion les bénéfices depuis une perspective stratégique. Pour les détails vous devrez examiner le guide de praticien Managing Benefits.

Dans le guide de manager, vous trouvez une explication sur les bénéfices et leur management. Le management des bénéfices est positionné dans le contexte organisationnel et le cycle de management des bénéfices. Ce cycle Identifier et Évaluer quantitativement – Estimer et Évaluer, Planifier – Réaliser er revoir est comparable avec le cycle des bénéfices de MSP Identifier – Planifier – Réaliser er revoir.

Un chapitre séparé se concentre sur la nécessité du management des bénéfices et ce que vous obtiendrez en retour.

On y explique quatre barrières au succès et comment les surmonter :

  • fausses idées communes sur la réalisation de bénéfices
  • l’écart en savoir et faire
  • le biais cognitif
  • les pressions organisationnelles
MS Project

Partenaire de DantotsuPM

Comme dans beaucoup d’autres méthodes la fondation pour le management des bénéfices est basée sur sept principes :

  1. aligner les bénéfices sur la stratégie
  2. débuter avec l’objectif final à l’esprit
  3. utiliser des méthodes de livraison qui marchent
  4. intégrer les bénéfices dans le management des performances
  5. gérer les bénéfices d’une perspective de portefeuille
  6. appliquer une gouvernance efficace
  7. développer une culture de valeur

Un chapitre intéressant est celui sur les problèmes qui peuvent avoir un impact sur l’efficacité du management des bénéfices. Pour chaque problème, vous trouverez une ou plusieurs techniques pertinentes pour leur faire face.

Finalement vous pourrez réaliser une très simple évaluation de santé de votre management des bénéfices en répondant à 10 questions.

En conclusion, ce petit livret donne une bonne vue d’ensemble du praticien du guide Managing Benefits et vous aidera à obtenir une meilleure compréhension ce que cela signifie que d’utiliser des pratiques et des techniques de management des bénéfices dans votre organisation.

Plus d’informations sur : http://www.apmg-international.com/en/qualifications/managing-benefits/managing-benefits.aspx

Partenaire de DantotsuPM

Partenaire de DantotsuPM

Précédent billet sur cette méthode:

28 Janvier – Toulouse – Value-Driven Project Management with Frank Saladis

20 Jan

PMIFR_Logo-Midi-PyreneesLa Branche Midi-Pyrénées du Chapitre PMI France vous invite à cette conférence exceptionnelle (en anglais) qui commencera à 18:00 à Toulouse-Blagnac. Lieu exact à confirmer.

Responding to the needs of today’s project managers, Value-Driven Project Management begins by changing the paradigm of project management. Rather than judge the success of a project from the perspectives of time, budget, and quality, the authors demonstrate why success is only achieved when planned business values are met, including concepts as Internal value, Future value and Customer-related value.

Frank Saladis

Frank Saladis

Frank P. Saladis, PMP®, is a Consultant and Instructor / Facilitator within the project management profession.  He is a Project Management Professional and has been a featured presenter at the Project Management Institute ® Annual Symposia and World Congresses and many other project management events. Mr. Saladis is a graduate of the PMI Leadership Institute Masters Class and has held several positions within The Project Management Institute including President of the NYC Chapter, President of the Assembly of Chapter Presidents and Chair of the Education and Training Specific Interest Group. Mr. Saladis held the position of editor of the internationally distributed newsletter for allPM.com from 2004 to 2011 and is the author of several project management books and numerous articles about project leadership. Mr. Saladis is the originator of International Project Management Day and was recognized as PMI Person of the Year for 2006.

Les inscriptions se font sur le site Internet du PMI France.

September 12 – Switzerland (Geneva) – Achieving Business Agility

29 Août

A PMI Switzerland event

Achieving Business Agility – Benefits from Portfolio, Program and Project management

SMPP

Partenaire de DantotsuPM

Several surveys show that most major companies spend between 1% and 6% of their turnover on change, and this typically equates to between 10% and 60% of their profit. At the same time, repeated surveys show that much of the money spent in this way is wasted – especially where the change is based upon the use of information technology. Repeated surveys show that as few as 20% of change initiatives are deemed to be fully successful and that many will be abandoned after consuming an enormous amount of time, money and effort. In the UK it is estimated that half of the £100billion spent annually on change is wasted and the equivalent figure for 400 leading European companies is approximately €300 billion.

This thought provoking presentation will stretch the audience thinking to answer on how a benefits and business value driven approach can accelerate your organization’s development and growth. It will deliver proven cases and methodologies, with focus on benefits realization.

christian de loesChristian de Loës, Managing Director, Prosensit Management Consulting AB, has more than 20 years international experience of defining, advising and leading successful change in businesses and organizations of all sizes and many sectors, at senior management level. Christian de Loës’s

experience ranges from Business Development and Sales trough Portfolio-, Program- and Project Management. One of his specialties is growing Sales through enabling Sales Excellence, Turnarounds and expansions into new territory, in an international setting. He is also frequent international speaker on subjects related to achieving Sales Excellence and increased project maturity across organizations.

Agenda:

18.00 Registration

18.30 Presentation

19:30 Q&A

20.00 Networking Apéro

Venue: Hotel Bristol, Rue du Mont-Blanc 10, 1200 Genève

Register

manager les bénéfices : «Managing Benefits»

20 Juil

Managing Benefits

http://www.apmg-international.com/home/Qualifications/ManagingBenefitsQuals.aspx

APMG Managing Benefits

« Managing Benefits » est le  dernier guide de conseils de APMG-INTERNATIONAL. Le but est de fournir aux managers et praticiens de multiples disciplines, travaillant dans une variété d’organisations, des conseils généralement applicables englobant des principes, des pratiques et des techniques de management des bénéfices.

« Managing Benefits » fournit:

  • Une vue d’ensemble de la gestion des bénéfices. Ce que c’est, la raison de le faire, et quelques idées communes mais fausses qui peuvent limiter son efficacité dans la pratique.
  • Les descriptions des sept principes sur lesquels des approches réussies de management des bénéfices sont construites et des exemples de comment elles peuvent être appliquées en pratique.
  • Des conseils sur la façon d’appliquer le management des bénéfices au niveau d’un portefeuille de projets, aussi bien qu’à un projet individuel ou au niveau d’un programme.
  • Les détails des cinq pratiques du Cycle de management des bénéfices et des exemples concrets de comment elles peuvent être été appliquées.
  • Des conseils sur la façon de commencer dans l’implémentation de pratiques de management des bénéfices efficaces et de continuer à progresser.

Lisez/téléchargez le Managing Benefits Certification Leaflet.

QRP International France

Partenaire de DantotsuPM

Il y a un facteur primordial à la base de la décision de produire le guide. Les bénéfices ne sont pas simplement un aspect du management de projet et de programme (PPM), ils sont plutôt la raison d’investir des fonds des contribuables et actionnaires dans les initiatives de changement.

Ce nouveau guide a été soigneusement conçu en complément aux meilleures pratiques de management de Portefeuille, Programme et Projet (comme PRINCE2 ®, MSP ®, P3O ® et MoP™). Il consolide des conseils existants sur le management des bénéfices en un seul endroit, tout en couvrant les pratiques et les techniques spécifiques visant à optimiser la réalisation des bénéfices.

Pourquoi ?

Les raisons pour lesquelles des organisations et gouvernements investissent dans des projets et des programmes sont de réaliser des bénéfices en terme de :

  • Accroissement du revenu;
  • Économies par une plus grande efficacité;
  • Livraison d’une contribution tangible à une priorité d’affaires ou objectif stratégique;
  • Réponse à une disposition réglementaire ou légale ou pour maintenir le business.

Pourtant, les rapports d’organismes professionnels, d’agences d’audit et la recherche universitaire montrent que les organisations dans le public, privé et les secteurs tertiaires continuent à avoir du mal à démontrer un retour sur leurs investissements dans le changement.

La signification de ceci est encore plus grande dans un climat économique volatil où l’échec à optimiser la réalisation des bénéfices peut fort bien mettre des initiatives futures en danger car les investisseurs perdent leur confiance en la capacité de l’organisation à manager le changement.

Microsoft Project

Partenaire de DantotsuPM

Pour qui ?

Le guide est pertinent pour tous les secteurs et types de projet ou programme, ce que le guide appelle des « initiatives de changement ».

L’audience cible englobe donc tous ceux qui ont un rôle dans s’assurer que l’utilisation des fonds des contribuables et/ou actionnaire est optimisée en maximisant les bénéfices réalisés par les initiatives de changement. Ce groupe multidisciplinaire inclut:

  • Les leaders de changement (par exemple les propriétaires responsables et les directeurs de changement)
  • Les initiateurs de changement (des planificateurs stratégiques par exemple et leaders de politiques)
  • Les experts et estimateurs de changement (des développeurs de cas d’affaire / business case par exemple et auditeurs de projets)
  • Les réalisateurs/activateurs du changement (par exemple, les managers de Portefeuilles, Programmes et Projets)
  • Les équipes de support au changement (par exemple, le personnel des bureaux de portefeuille, programme et projet)
APMG International France

APMG International est partenaire de DantotsuPM

July 24 – Webinar (PMI) – Value Management

13 Juil

Register Today for 24 July PMI IT and Telecom Community of Practice Webinar

Topic: « Value Management« , Presenter: Benjamin Govindsamy

24 July 2013 • 10 – 11 AM EDT (4PM CET/France)


valueIn an economy where doing more with less has become the order of the day and where value realization has the strongest focus, our project portfolio and project management practices must reflect and support rigorous processes that seek out maximum value. This presentation explores an overview on value drivers and best practices for measuring and delivering value. Learn more about value management and how to ensure value delivery on projects.

Ben Govindsamy has acquired a wealth of experience in variety of industries that include, wholesale & retail, government, mining & manufacturing and financials. He currently fulfills a role as performance assurance systems manager. This entails IM KPI Performance tracking, trending, reporting. Through consultation with various levels of management, Ben ensures the relevance, alignment & success of the Global IM Strategic Targets.

July 2 – Webinar (PMI) – Program Management – Mission Accomplished – Benefits Realized

28 Juin

Organizational Project Management Community of Practice (OPM CoP) proposes a new webinar:

Executive Value / Executive Positioning and Organizational Governance with “Program Management – Mission Accomplished – Benefits Realized  by former OPM CoP Council Lead: Russ McDowell, M. Eng., PMP, PRINCE2, OPM3P

2nd July 2013 17:00 CET (Paris)

The purpose of this webinar is to debate how to identify current challenges that organizations are having and to suggest implementation approaches of Benefits Management in today’s organizations.

OPM3 par PMIRuss McDowell is an independent consultant responsible for the set-up or management of numerous project offices, definition of project management frameworks, as well as the management of successful projects. He has contributed to the development of the field of “Organizational Project Management” through roles as:
• Past Chair of PMI’s worldwide Community of Practice for Organizational Project Management,
• Co-author of the book “Organizational Project Management – Linking Strategy and Projects” published in 2010,
• One of PMI’s original instructors for their SeminarsWorld ® course titled: “OPM – Where do Good Projects Come From?”, and
• Cited in three OPM-related PMI standards for his contributions in the development of: the Portfolio Management Standard, the Program Management Standard, and the OPM Maturity Model (OPM3)

 